In Namibia, any activity on the government's list, from storing more than 30 cubic metres of fuel at one site to building an oil or gas pipeline, needs an environmental clearance certificate from the Environmental Commissioner under the Environmental Management Act 7 of 2007. As of 26 November 2026, a certificate lasts at most three years.
Key facts
- The Environmental Management Act 7 of 2007 came into force on 6 February 2012, the same day the list of activities (Government Notice 29 of 2012) and the Environmental Impact Assessment Regulations (Government Notice 30 of 2012) were published (Government Gazette 4878).
- Carrying out a listed activity without a certificate is an offence, with a fine of up to N$500,000, up to 25 years in prison, or both (section 27(4) of the Act, LAC annotated text).
- Applications go through the environment ministry's online ECC Portal. Its fees on 26 November 2026 were N$300 to apply, N$300 to amend, N$1,000 to transfer and N$1,000 to appeal (ECC Portal).
- On 26 November 2026 the portal's public list of decided applications held 3,878 application numbers. CrewDog counted 35 linked to upstream oil and gas: 18 seismic surveys, 10 well-drilling files and 7 onshore support facilities. All 35 showed "APPROVED" (method below).
What is an environmental clearance certificate?
It is, in the ministry's words, "an authorisation to undertake a listed activity". The Act lets the minister list activities that "may not be undertaken without an environmental clearance certificate" (section 27). Two rules give it teeth:
- No certificate, no activity. Undertaking a listed activity without one is an offence (section 27(4)).
- No certificate, no other permit. Another authority "may not issue an authorisation" for a listed activity unless the applicant already holds a clearance certificate, and a permit issued without one is invalid (section 31).
Breaking a condition of a certificate is also an offence: up to N$500,000 or 25 years where no full assessment was needed (section 34(3)), and up to N$500,000 or 20 years after a full assessment (section 37(3)). Giving false information in an application can bring up to N$100,000 or ten years (section 43).
Check the current text, or ask a Namibian lawyer, before relying on it.
Which oil and gas activities need one?
The 2012 list does not mention exploration, seismic surveys or drilling. Items relevant to oil and gas work and its suppliers include:
- 1(c): building facilities for refining gas, oil and petroleum products.
- 2.1 and 2.3: waste sites and treatment, and the import, processing, temporary storage, transit or export of waste.
- 3.2 to 3.4: other mining or extraction of natural resources, resource extraction, and extracting or processing gas.
- 9.1, 9.3 and 9.4: handling hazardous substances; moving dangerous goods by pipeline at 50 tonnes or 50 cubic metres a day or more; storing dangerous goods such as diesel in containers of more than 30 cubic metres combined at one site.
- 10.1(a), (c) and (e): building oil and gas pipelines, harbours, and "any structure below the high water mark of the sea".
How applicants use the list shows in a real file. An application on the portal for an exploration well in Block 2914A, offshore southern Namibia, cited items 2.2, 2.3, 3.2, 3.3, 3.4, 9.1, 9.3, 9.4 and 10.1(e), the last because a wellhead is placed on the seabed and left there after the well is abandoned. Its status shows as approved (ECC Portal, application 231107002431).
The portal also offers a screening questionnaire to help work out whether a project needs an assessment.
Check the current text, or ask a Namibian lawyer, before relying on it.
How does the process work?
The Act and the 2012 regulations set these steps:
- Appoint an environmental assessment practitioner (EAP). The proponent must name one to manage the assessment and pays for it (regulation 3).
- Apply. Register the project on the ECC Portal and apply on Form 1 to the "competent authority", which forwards it to the Environmental Commissioner (section 32, regulation 6).
- Consult the public. Put up a notice board at the site, write to neighbours and the local, regional and traditional authorities, and advertise once a week for two weeks running in two widely read newspapers. Keep a register of interested and affected parties (regulations 7, 21 and 22).
- Submit a scoping report. It describes the activity, the site, the likely effects, alternatives and the consultation, and proposes terms of reference for any detailed assessment (regulation 8).
- The Commissioner decides whether a full assessment is needed (section 33). If not, the Commissioner can grant or refuse (section 34). If so, the Commissioner sets the scope, the proponent's EAP prepares an assessment report, the public can comment, and the Commissioner may hold a public hearing (sections 35 and 36).
- Decision. The Commissioner grants a certificate, with any conditions, or refuses with reasons (section 37). The regulations give seven days after the review to notify the decision (regulation 18).
- After the decision. A certificate lasts no more than three years (section 40). It cannot be transferred without the Commissioner's permission (section 41), its conditions can be amended (section 39), and it can be suspended or cancelled (section 42).
- Appeals. Anyone aggrieved by the Commissioner's decision can appeal to the minister (section 50), and then to the High Court on points of law only (section 51).
Who is the Environmental Commissioner?
An official appointed by the environment minister, with a deputy (section 16). The Commissioner's duties include receiving applications, deciding whether an assessment is needed and what it covers, reviewing assessment reports, issuing certificates, keeping registers of assessments and certificates, and inspecting for compliance (section 17). In practice the work sits in the Department of Environmental Affairs of the Ministry of Environment, Forestry and Tourism, which runs the ECC Portal. The ministry says it reviews assessments; it does not carry them out.
Check the current text, or ask a Namibian lawyer, before relying on it.
What does an offshore oil and gas assessment look like?
The Venus field development shows the full process. TotalEnergies EP Namibia's page says its practitioner, SLR Environmental Consulting (Namibia), finished the scoping phase with public consultation and then put the full environmental and social impact assessment out for public comment from 3 November to 3 December 2025. It held meetings in Keetmanshoop, Bethanie, Lüderitz, Oranjemund, Windhoek, Henties Bay, Swakopmund and Walvis Bay, plus online sessions on air emissions, marine ecology and fisheries, and social and economic impacts (TotalEnergies Namibia). Separately, TotalEnergies says it spent over $5 million on environmental baseline surveys of Blocks 2912 and 2913B before its main exploration work.
Status as of 26 November 2026: we did not find a Venus development entry among the decided applications on the ECC Portal. The project's investment decision is covered in TotalEnergies in Namibia.
What the ECC Portal shows: 35 upstream oil and gas files
Method. On 26 November 2026 we read the portal's public list "Approved and rejected Applications" (3,878 application numbers). We searched the titles for exploration terms (petroleum exploration licence, PEL, seismic, exploration or appraisal well, offshore, oil and gas), opened each match, and kept those tied to upstream oil and gas. We left out fuel depots, filling stations, refineries, bunkering and marine diamond mining.
Result:
- 16 offshore seismic surveys, many of them multi-client surveys over several licence blocks.
- 2 onshore seismic surveys, in the Owambo basin (PEL 93) and in PEL 73.
- 10 exploration or appraisal well-drilling files: 9 in PEL 39, PEL 44, PEL 82, PEL 83, PPL 003 and Blocks 2813B, 2912, 2913B and 2914A, and 1 onshore, in the Kavango basin.
- 7 support facilities on land: stores for drilling and exploration chemicals at Lüderitz and Walvis Bay, an oil and gas waste facility at Lüderitz, two warehousing files for land on Farm 38 at Walvis Bay, and a logistics base and a supply base at Lüderitz.
All 35 showed "APPROVED". Ten are renewals or amendments of earlier certificates. For 7 of the 35, the "valid until" date had already passed by 26 November 2026; the list does not show whether a later certificate replaced them.
What it means for suppliers. Clearance is not only for oil companies. Stores, waste plants, warehouses and bases serving the industry have gone through the same process. For the Lüderitz plans, see the Lüderitz supply base.
What should a supplier check?
- Is your own work on the list? Fuel storage over 30 cubic metres, waste handling or building on the shoreline may need your own certificate. Use the portal's screening questionnaire.
- What does the buyer ask for? NAMCOR's 2025 form for petroleum product suppliers asks for certified copies of "Environmental Compliance Certificates". TotalEnergies' 2025 call for onshore drilling waste services required an environmental baseline study and an environmental impact assessment for a landfill site near Lüderitz, plus a municipal permit for hazardous waste.
- Can you prove it? The portal has a page to verify a certificate by its serial number.
- When does it expire? Diary the date: three years at most.
- Who does the assessment? You appoint and pay the EAP.
Is the law about to change?
The ECC Portal offers a draft Environmental Management Amendment Bill for download. The copy is marked "Draft Bill as @ 23 February 2021". Among other things, it would let a certificate last up to five years, require renewal applications 90 days before expiry, set up registration of environmental assessment practitioners and add strategic environmental assessment.
Status as of 26 November 2026: the portal offers it as a draft, and we found no amending Act. Treat the three-year limit in section 40 as current unless a lawyer tells you otherwise. For the wider picture of who regulates the sector, see who regulates oil and gas in Namibia.
Check the current text, or ask a Namibian lawyer, before relying on it.
Where CrewDog fits
CrewDog's directory lists 6 companies under environmental and waste services, from named public sources reviewed on 15 November 2026, on the Namibia companies page. Environmental and waste contracts from NAMCOR and Namport appear, when issued, on the Namibia tenders page.
Sources
- Government Gazette of the Republic of Namibia No. 4878 (GN 28, 29 and 30 of 2012), 6 Feb 2012, copy on Gazettes.Africa: https://archive.gazettes.africa/archive/na/2012/na-government-gazette-dated-2012-02-06-no-4878.pdf
- Legal Assistance Centre, Environmental Management Act 7 of 2007 (annotated statute, file dated Nov 2020), read 26 Nov 2026: https://www.lac.org.na/laws/annoSTAT/Environmental%20Management%20Act%207%20of%202007.pdf
- Ministry of Environment, Forestry and Tourism, Department of Environmental Affairs, ECC Portal (home, FAQs, fees, downloads), read 26 Nov 2026: https://eia.meft.gov.na/
- Ministry of Environment, Forestry and Tourism, ECC Portal, Approved and rejected applications, read 26 Nov 2026: https://eia.meft.gov.na/web/cleared
- Ministry of Environment, Forestry and Tourism, ECC Portal, application 231107002431 (exploration well, Block 2914A), read 26 Nov 2026: https://eia.meft.gov.na/web/projects/2431
- Ministry of Environment, Forestry and Tourism, ECC Portal, Environmental Management Amendment Bill (draft as at 23 Feb 2021), read 26 Nov 2026: https://eia.meft.gov.na/downloads/23
- TotalEnergies EP Namibia, ESIA for Proposed Development of the Offshore Venus Field in Block 2913B, read 26 Nov 2026: https://totalenergies.na/esia-proposed-development-offshore-venus-field-block-2913b
- TotalEnergies EP Namibia, Environmental Baseline Survey, read 26 Nov 2026: https://totalenergies.na/environmental-baseline-survey
- TotalEnergies EP Namibia, Expression of Interest for Onshore Drilling Waste Management Services, closing 1 Aug 2025: https://dxm.content-center.totalenergies.com/api/wedia/dam/variation/xysh7dg731ta7fieycc713fziy/original,default?hash=gy316cbzfh3dyctiryauyqtt8y7dyqe&dxm_cors_orign=76ABE9E30D5586637AC358998F93E703
- NAMCOR, KYC Form for Petroleum Suppliers, 2 Sep 2025: https://www.namcor.com.na/wp-content/uploads/2025/10/Petroleum-Suppliers-for-NAMCOR-V1-02092025.pdf
How this was made: researched from the sources listed above, with AI help for drafting. See how we write our articles.