As of 26 November 2026, the Kudu gas-to-power project has no final investment decision. BW Energy, which runs the field, is looking for a partner to buy into the licence and expects that sale to complete in the second half of 2027. Its appraisal drilling is on hold meanwhile, and it gives no date for first gas or power.
Key facts
- The field: discovered in 1974, about 130 km off the southwest coast of Namibia in about 170 m of water, in the northern Orange Basin (BW Energy reserves statement 2025).
- The owners: BW Energy holds 95% and operates Petroleum Production Licence 003 (PPL003). NAMCOR holds 5%, with the right to take another 5% at first gas, subject to conditions (same source).
- The size: consultants Netherland, Sewell & Associates estimate gross best-case contingent resources of 170.0 million barrels of oil equivalent, all gas, as of 30 June 2022. These are not reserves (same source).
- The power licence: the Electricity Control Board's list, updated February 2026, shows a 420 MW gas-fired generation licence held by BW Kudu Limited, at "Luderitz, Karas Region", with offtakers "NamPower and SAPP", status "Not-Operational" and start date "TBC" (ECB).
- The latest: on 29 October 2026 BW Energy said about 50 companies were in talks and about 20 had signed non-disclosure agreements for its stake sale, with completion "expected in the second half of 2027" (BW Energy Q3 2026 report).
Status as of 26 November 2026: no final investment decision, no first-gas or first-power date, and no signed power purchase or gas sales agreement in BW Energy's published reports.
What is Kudu?
Kudu is a gas field, not an oil field, in shallower water than the recent oil finds. NAMCOR's history page says the discovery well, Kudu 9A-1, was drilled by Chevron, Regent and SOEKOR. It adds that in 1987 and 1988 SWAKOR, NAMCOR's predecessor, drilled two more wells, one of which "proved a dry gas discovery" (NAMCOR history). After independence Shell held a licence over the field. BW Energy says the field is "delineated by seven subsequent wells".
Plans to turn Kudu gas into electricity are old. A NamPower background paper from about 2004 described a "nominal 800 MW" combined-cycle power station at Oranjemund fed by Kudu gas (NamPower, archived copy). It was never built.
BW Energy took an operating interest in 2017 and signed a deal to raise its stake to 95% on 14 January 2021 (BW Energy). It drilled the Kharas-1A appraisal well in 2025. BW says the well "confirmed multiple source rocks and the presence of light oil/condensate in addition to the proven Kudu gas discovery" (Q3 2026 report).
What is the gas-to-power plan?
BW Energy's current outline, in its reserves statement published in February 2026, has four parts:
- Three subsea wells tied back to a floating production unit, which would be a semi-submersible drilling rig converted for the job.
- A gas export pipeline to a power plant.
- The power plant, then an onshore substation.
- Transmission into the Namibian grid.
NAMCOR's upstream page, which is undated, gives more detail on an earlier version of the concept. It describes a 195 km pipeline to Elizabeth Bay, near Lüderitz, feeding a power plant on a jack-up barge near the shore, "targeting at least 420Mw (phase 1)". It says both NamPower and regional markets are targeted (NAMCOR). The regulator's licence, also 420 MW at Lüderitz, is held by BW Kudu Limited, not NamPower.
Who would buy the power?
The licence names NamPower, the national power utility, and SAPP, the Southern African Power Pool, as offtakers. No sales contract has been announced. BW Energy said in February 2023 that it was "negotiating heads of terms" with "the local power company", and that sanction depended on project financing and on "negotiating power sales agreements" (BW Energy Annual Report 2022). Its later wording is softer. In its 2025 annual report it said it progressed the project "in close dialogue with Namibian authorities and the local power company". In October 2026 it said: "Dialogue with government over gas to power project continues actively" (BW Energy Q3 2026 presentation).
NamPower's own integrated annual reports for 2024 and 2025 do not mention Kudu by name; we searched their full text.
Why does Namibia want it?
Because Namibia imports much of its electricity. NamPower's 2025 annual report, for the year to 30 June 2025, says local generation supplied 51% of the country's energy needs and regional imports 49% (NamPower Integrated Annual Report 2025). In a September 2026 speech printed by The Namibian, NamPower's managing director, Kahenge Haulofu, said imports "average 50% per year and up to 70% during dry seasons". He added that regional trading would continue "until we put in place a baseload power plant" (The Namibian, 30 Sep 2026).
The project also has political backing across the border. After their meeting in Pretoria on 17 July 2026, the presidents of South Africa and Namibia agreed to deepen energy cooperation, "including by accelerating the implementation of the Kudu Gas Power Project" (joint communiqué).
Where does the project stand now?
BW Energy's three 2026 updates tell the story, latest first:
- 29 October 2026: the stake sale is running. The first phase continues into December 2026 and a second phase with selected parties follows in early 2027. The Kudu appraisal programme "remains on hold while the process is ongoing" (Q3 2026 report).
- 30 July 2026: BW started the data room process in June (BW Energy Q2 2026 report).
- 20 May 2026: BW presented Kudu as "the natural LNG and power hub for Orange Basin", with "neighbouring associated gas to scale", meaning gas produced alongside oil at nearby fields. It also gave a management estimate of about 1.5 trillion cubic feet of recoverable gas (BW Energy strategy update).
None of these reports gives a date for an investment decision or for first gas. If you see a date in a news report, check it against BW Energy's latest quarterly report.
What has to happen before Kudu power flows?
This is our checklist, built from BW Energy's reports and the regulator's list. Each item gives its status on 26 November 2026:
- A partner joins. Status: talks under way; completion, including government approvals, expected in the second half of 2027 (BW Energy, 29 Oct 2026).
- Appraisal restarts. Status: on hold until the stake sale is done (same source).
- Power and gas sales agreements. Status: "dialogue" with the government; no signed agreement published (BW Energy, Oct 2026).
- Financing. Status: no financing announced. BW said in 2023 that sanction depended on a project financing solution (Annual Report 2022).
- A final investment decision. Status: not taken; no target date published.
- Environmental clearance for the development. Status: the clearance we found covers appraisal drilling only. The environment ministry's register shows it approved for "appraisal well drilling" in PPL 003 (MEFT). BW notes the field lies "almost entirely" within the Orange Seamount and Canyon Complex, an area listed as ecologically and biologically significant (BW Energy Annual Report 2025).
- The build. Status: not started. Wells, the converted rig, the pipeline, the power plant and the grid connection all follow a decision.
- A generation licence. Status: held. The regulator lists BW Kudu's 420 MW licence as "Not-Operational" (ECB, February 2026).
What does this mean for suppliers?
Most Kudu work, from the wells to the power plant, follows an investment decision (see the checklist above). What is public so far is small. CrewDog keeps a record of contract awards published by NAMCOR and Namport. In it, NAMCOR Exploration and Production's notice of 3 September 2025 selected Xodus as consultant for a "Gas Monetization Strategy" (reference SC/RP/NC-06/2024) (NAMCOR notice). The notice does not say which gas it covers.
On 26 November 2026, none of the 33 tender notices and 169 awards in our record mentioned Kudu. Our record covers NAMCOR and Namport only, not NamPower or BW Energy. To follow what is open, see our tenders page, and for past awards, our contract awards page.
For how Kudu fits with Namibia's oil projects, see When will Namibia produce oil? and How much oil does Namibia have?. For the port side of Lüderitz, see Lüderitz and oil and gas.
Sources
- BW Energy, Annual Statement of Reserves 2025, Feb 2026: https://storage.mfn.se/aa8125ad-1f31-4e3f-90fd-d194c8735961/bw-energy-annual-statement-of-reserves-2025.pdf
- BW Energy, third quarter 2026 report, 29 Oct 2026: https://storage.mfn.se/d7a6058d-6d57-44c8-bc67-ccfeae5a5235/bw-energy-financial-report-q3-2026.pdf
- BW Energy, Q3 2026 presentation, 29 Oct 2026: https://storage.mfn.se/66803ce0-a5e7-4c1a-812c-0c7d9deab44d/bw-energy-q3-2026-presentation.pdf
- BW Energy, second quarter and first half 2026 report, 30 Jul 2026: https://storage.mfn.se/3c911f93-486a-4020-b456-06a74e91db49/bw-energy-financial-report-q2-and-h1-2026.pdf
- BW Energy, Q1 2026 and strategy update presentation, 20 May 2026: https://storage.mfn.se/a5f4f384-9164-4270-a33e-33e90dfa59f4/q1-2026-and-strategy-update-final.pdf
- BW Energy, Annual Report 2025, 27 Feb 2026: https://storage.mfn.se/184943a2-7817-4a56-b178-c117c0646e9e/bw-energy-annual-report-2025.pdf
- BW Energy, Annual Report 2022, 28 Feb 2023: https://live.euronext.com/sites/default/files/company_press_releases/attachments_oslo/2023/02/28/583764_BW%20Energy%20Annual%20Report%202022.pdf
- BW Energy, BW Energy signs Kudu farm-in agreement, 14 Jan 2021: https://www.bwenergy.no/en/bw-energy-signs-kudu-farm-in-agreement/
- Electricity Control Board, Generation and other licences issued (updated February 2026): https://www.ecb.org.na/wp-content/uploads/2026/03/Generation_and_other_licences_issued_-Feb_2026.pdf
- NAMCOR, History, read 26 Nov 2026: https://www.namcor.com.na/history/
- NAMCOR, Upstream development and production, undated, read 26 Nov 2026: https://www.namcor.com.na/upstream-development-production/
- NamPower, Kudu background information (archived copy), about 2004: https://web.archive.org/web/20120306150308/http://www.nampower.com.na/docs/Kudu-Background%20Information.pdf
- NamPower, Integrated Annual Report 2025 (year to 30 Jun 2025), 2026: https://www.nampower.com.na/Media/Document/108386cd-c2b5-4861-97ac-69a0eea46309.pdf
- The Namibian, NamPower reflects on 30 years of growth as it launches new strategic plan, 30 Sep 2026: https://www.namibian.com.na/nampower-reflects-on-30-years-of-growth-as-it-launches-new-strategic-plan/
- The Presidency of South Africa, Joint communiqué of the fourth session of the South Africa-Namibia Bi-National Commission, 17 Jul 2026: https://thepresidency.gov.za/sites/default/files/2026-07/SA%20NAM%20Joint%20Communique.pdf
- Ministry of Environment, Forestry and Tourism, EIA register entry 240828004608, read 26 Nov 2026: https://eia.meft.gov.na/web/projects/4608
- NAMCOR Exploration and Production, notice to bidder selected for the award, SC/RP/NC-06/2024, 3 Sep 2025: https://www.namcor.com.na/wp-content/uploads/2025/09/Bid-Outcome-SC-RP-NC-062024-Selection-of-Consultant-for-Gas-Monetization-Strategy.pdf
- CrewDog, Namibia tenders and contract awards pages, data as of 26 Nov 2026: https://www.crewdog.ai/namibia/contract-awards
How this was made: researched from the sources listed above, with AI help for drafting. See how we write our articles.