As of 26 November 2026, Namibia produces no oil, and no oil field has a final investment decision (FID), the point at which the owners commit the money to build. The nearest is TotalEnergies' Venus field. In February 2026 TotalEnergies linked first oil in 2030 to a decision by mid-2026, and that decision has not come.
Status as of 26 November 2026: no final investment decision has been announced for Venus or any other Namibian oil field, so no first-oil date is confirmed. Every decision or first-oil date below is a target that a company or official has stated, shown with who said it and when.
Key facts
- Venus: on 11 February 2026 TotalEnergies said it was working towards "an FID by mid-2026, allowing a first oil in 2030" (TotalEnergies results transcript, 11 Feb 2026).
- Venus, latest: on 29 October 2026 chief executive Patrick Pouyanné said "we are optimistic to reach the FID" (TotalEnergies Q3 transcript, 29 Oct 2026). None of the company's press releases from 30 October to 23 November 2026 mentions Namibia (TotalEnergies press releases, read 26 Nov 2026).
- Mopane: TotalEnergies, operator since early September 2026, aims to sanction it "by 2028", and has said Mopane's production is "beyond 2030" (28 Sep 2026; 23 Jul 2026).
- Government: The Namibian reported on 4 October 2026 that Namibia was targeting first oil in 2030, "subject to FID and the necessary approvals" (The Namibian).
- Kudu gas: BW Energy gives no decision or first-gas date. It expects to bring in a partner, with completion in the second half of 2027 (BW Energy Q3 2026 report, 29 Oct 2026).
Why is there no confirmed date?
Because first oil follows an investment decision, and no Namibian field has one. For Venus, TotalEnergies says the engineering is ready and the open point is the agreement with the government. On 23 July 2026 Pouyanné told investors the company was "ready to take the FID, subject to finalizing discussions with the government of Namibia" (TotalEnergies Q2 transcript).
In September he added that Venus is "a more complex field because of a lower permeability" (oil flows less easily through the rock), and that the partners want to protect the project's returns if oil prices fall, which was under discussion with the authorities. He said they were "working to sanction the project in the coming months" (TotalEnergies, 28 Sep 2026).
The government has said little in public about timing. Asked in October whether the decision would come in 2026, Kornelia Shilunga, head of the Upstream Petroleum Unit in the Presidency, said: "That's a question for Total" (World Oil, 15 Oct 2026). How the Venus decision target moved through 2025 and 2026 is set out date by date in our Venus article.
What has each project said about first oil?
This is our tracker of what each operator has said in public, in date order within each project. It covers each offshore licence with a published discovery, plus the onshore Kavango well.
- Venus (PEL 56, TotalEnergies operator). In February 2026: first oil "in 2030", assuming a mid-2026 decision. On 23 July 2026 Pouyanné said "Venus should start by end 2030" (Q2 transcript). That is the latest first-oil date we found from TotalEnergies itself, and it was given while the decision was still aimed at the end of July. African Energy Week's report of a 15 October session with TotalEnergies Namibia's managing director, Mariam Kane Garcia, describes the project as "targeting first oil around 2030", and quotes her: "Any delay will increase the cost of CAPEX", meaning the capital cost (African Energy Week).
- Mopane (PEL 83, TotalEnergies operator, with Galp). In February 2026 TotalEnergies said Mopane would contribute "in production beyond 2030". On 28 September 2026 Pouyanné said three wells would be drilled from a rig due in mid-November, aiming to sanction Mopane "by 2028". On 29 October he said "we are starting the drilling of the Mopane well this month". No first-oil year has been given.
- Capricornus and the rest of PEL 85 (Rhino Resources operator, with Azule Energy). Rhino's project page says "Appraisal and development planning are now under way" after the Capricornus-1A appraisal well in 2026, and its company profile states an ambition of "being 1st to first oil". We found no first-oil year on Rhino's own site (Rhino Resources, read 26 Nov 2026). Under the farm-out, Azule Energy has the option to become operator for the development phase (Rhino Resources).
- Shell's PEL 39 (Graff, Jonker, Merlin and other wells). No development plan. On 9 June 2026 Shell said Merlin-1X gave "the most promising subsurface results to date" in the licence, that it was working "to establish commerciality", and that more drilling later in 2026 was "under consideration" (Shell Namibia). In January 2025, after six exploration and three appraisal wells, NAMCOR pointed to "ultra-deepwater conditions and reservoir complexities" (NAMCOR, 10 Jan 2025).
- Kudu (gas, BW Energy operator). This is gas for power, not oil. BW Energy's latest report gives no decision or first-gas date, and its appraisal drilling is on hold while it looks for a partner. The full picture is in the Kudu gas-to-power article.
- Onshore Kavango (PEL 73, ReconAfrica operator). Exploration only. ReconAfrica said on 18 August 2026 that the Kavango West 1X well "flowed natural gas and potential liquid content to surface", but "Flow rates were not measured" (ReconAfrica release, via energy-pedia).
What have the government and Namport said?
The government's stated aim, as reported, is first oil in 2030 if a decision and approvals come first. The same Namibian report says TotalEnergies is negotiating under the existing Petroleum (Exploration and Production) Act of 1991, and quotes the Presidency's spokesperson: the decision will be communicated "once both parties have reached an agreement" (The Namibian, 4 Oct 2026).
Namport, the state ports authority, has planned around the same project. Its October 2025 presentation on supply bases said the development and construction phase "will commence with TOTALENERGIES in 2027" and needs about ten times the port capacity of exploration (Namport, 6 Oct 2025). That was a planning assumption made a year ago. Its 2026 annual report now says the pace of port development depends partly on "the timing of oil companies' final investment decisions" (Namport Integrated Annual Report 2026).
How long does it take from a decision to first oil?
Years, not months. The Venus environmental study, prepared by SLR for TotalEnergies' Namibian subsidiary, sets out the steps after a decision (Venus ESIA non-technical summary, Oct 2025):
- Decision (FID). The partners commit the money.
- About a year later: offshore installation starts. It is spread over two southern-hemisphere summers because of sea conditions.
- About 18 months after the decision: development drilling starts and lasts up to four years, for up to 40 subsea wells.
- First oil. TotalEnergies' February 2026 plan put about four years between a mid-2026 decision and first oil in 2030.
- Production: about 21 years, with an option to extend by 10.
What else must be in place first, from the production ship to supply bases and a production licence, is in what Namibia must build before first oil.
What should suppliers and job seekers watch for?
These are the signals that would move a first-oil date from target to plan:
- A Venus decision announced by TotalEnergies or the Presidency.
- Namport's choice for the Lüderitz Bay supply base. Its request for proposals closed on 26 October 2026, and no award or cancellation was shown on 26 November 2026 (Namport).
- New tenders. CrewDog reads NAMCOR's and Namport's procurement pages every 12 hours. On 26 November 2026 our tenders page listed 14 open notices, 12 from Namport and 2 from NAMCOR.
- Hiring. On 26 November 2026 our jobs page listed 27 oil and gas adverts, 17 from employers directly and 10 from agencies, collected from employers' and agencies' own careers sites and checked every 12 hours.
If a decision comes, the Venus study estimates about 5,000 jobs during drilling and installation (500 direct, 2,000 at suppliers and 2,500 in the wider economy), and about 7,000 during production (600 direct, 600 at suppliers and 5,800 in the wider economy) (Venus ESIA non-technical summary). These are the study's estimates, not commitments.
Sources
- TotalEnergies, 2025 Results and 2026 Objectives presentation transcript, 11 Feb 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_2025-results-2026-objectives-transcript_2026_en.pdf
- TotalEnergies, 2Q2026 earnings call transcript, 23 Jul 2026: https://www2.totalenergies.com/sites/g/files/njizac106/files/documents/totalenergies_2q26-results-transcript_2026.pdf
- TotalEnergies, 2026 Strategy and Outlook presentation transcript, 28 Sep 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_transcript-strategy-and-outlook-presentation_2026_en.pdf
- TotalEnergies, 3Q2026 earnings call transcript, 29 Oct 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_3q26-results-transcript_2026.pdf
- TotalEnergies, press releases list, read 26 Nov 2026: https://totalenergies.com/news/press-releases
- The Namibian, "Treaty of Venus", 4 Oct 2026: https://www.namibian.com.na/treaty-of-venus/
- World Oil, TotalEnergies Namibia still negotiating Venus terms as 2026 FID target nears, 15 Oct 2026: https://www.worldoil.com/news/2026/10/15/totalenergies-namibia-still-negotiating-venus-terms-as-2026-fid-target-nears/
- African Energy Week, TotalEnergies Namibia's Venus project ready for sanction, 15 Oct 2026: https://aecweek.com/news/totalenergies-namibias-venus-project-ready-sanction-aew-2026
- Rhino Resources, Namibia project page, read 26 Nov 2026: https://www.rhinorsc.com/projects/namibia/
- Rhino Resources, Rhino Resources completes farm-out transaction with Azule Energy, undated: https://www.rhinorsc.com/rhino-resources-completes-farmout-transaction-with-azule-energy/
- Shell Namibia, Shell advances exploration in Namibia's Orange Basin with latest well results, 9 Jun 2026: https://www.shell.com.na/latest-stories/shell-advances-exploration-in-namibias-orange-basin-with-latest-well-results.html
- NAMCOR, NAMCOR position on PEL Block 39, 10 Jan 2025: https://www.namcor.com.na/wp-content/uploads/2025/01/PEL-39-Press-Release.pdf
- BW Energy, third quarter 2026 report, 29 Oct 2026: https://storage.mfn.se/d7a6058d-6d57-44c8-bc67-ccfeae5a5235/bw-energy-financial-report-q3-2026.pdf
- ReconAfrica (republished by energy-pedia), hydrocarbon flow to surface at Kavango West 1X, 18 Aug 2026: https://www.energy-pedia.com/news/namibia/reconafrica-announces-hydrocarbon-flow-to-surface-from-the-huttenberg-formation-at-kavango-west-1x--program-to-continue-with-open-hole-horizo-204987
- Namport, General ports update: oil and gas supply base focus, 6 Oct 2025: https://www.namport.com.na/files/procurement/87c_NAMPORT%20OIL%20AND%20GAS%20SUPPLY%20BASES%20-%206%20OCT%202025%20-%20V1.pdf
- Namport, Integrated Annual Report 2026 (year to 31 Mar 2026), Sep 2026: https://www.namport.com.na/files/documents/16c_Integrated%20Annual%20Report%20%202026.pdf
- Namport, RFP/OIB/NAMPORT-3768/2026 Lüderitz Bay Integrated Oil and Gas Supply Base, read 26 Nov 2026: https://www.namport.com.na/procurement/926/
- SLR Environmental Consulting (Namibia) for TotalEnergies EP Namibia, Venus Field Development ESIA non-technical summary, Oct 2025: https://cdn.sanity.io/files/b0ecix6u/production/5f020d69668168da7fc72e34ab92e96c8e40747d.pdf
- CrewDog, Namibia tenders and jobs pages, data as of 26 Nov 2026: https://www.crewdog.ai/namibia/tenders