As of 26 November 2026, most of what Namibia needs for its first oil is planned but not built, and much of it waits on the first final investment decision. For TotalEnergies' Venus field, the list runs from a floating production ship and up to 40 subsea wells to supply bases, port berths, trained people and a production licence.
Key facts
- The Venus plan: a floating production ship, up to 40 subsea wells (20 producing oil, 20 re-injecting gas), and shuttle tankers taking the oil to a transfer point about 20 km north of Walvis Bay (Venus ESIA non-technical summary, Oct 2025).
- Environmental clearance: the final environmental study has been submitted to the environment and energy ministries, and the clearance application was lodged on 25 February 2025. The consultant's page showed no decision on 26 November 2026 (SLR).
- Lüderitz Bay supply base: Namport's request for proposals for a concession of up to 25 years closed on 26 October 2026. No award or cancellation was shown on 26 November 2026 (Namport).
- Lüderitz port: Namport says its expansion plans "remain on track, albeit delayed by the pending conclusion of engagements with the Traditional Authorities" (Namport Integrated Annual Report 2026).
- The law: the Petroleum (Exploration and Production) Amendment Bill passed its second reading with 50 votes on 20 October 2026 and went to committee stage (The Namibian, 21 Oct 2026).
Status as of 26 November 2026: no final investment decision has been taken on any Namibian oil field. Most items below are designed, tendered or under negotiation, not built.
What does a deep-water oil field like Venus need?
Venus lies about 300 km off Oranjemund, 320 km from Lüderitz and 700 km from Walvis Bay, in about 3,000 m of water. Its environmental study, prepared by SLR for TotalEnergies' Namibian subsidiary, describes how it would work (non-technical summary linked above):
- A floating production, storage and offloading vessel (FPSO). This is a ship-shaped plant moored over the field. It separates oil, gas and water, and stores the oil.
- Subsea wells and pipework. Up to 40 wells, drilled by up to three rigs, are linked to the FPSO by flowlines, control cables and risers.
- No pipeline to shore. Gas goes back into the reservoir, with some used for power on board. About once a week at peak, a dynamically positioned shuttle tanker collects the oil. It carries it to a mooring buoy about 5 km off the coast north of Walvis Bay, where it is transferred to an ordinary tanker.
- Onshore support. Supply ships work from Lüderitz, the closest port, and Walvis Bay, "where main construction facilities are located". Offshore crews fly by helicopter "from existing airport facilities, mainly Lüderitz".
Our before-first-oil checklist
This is our list of what has to happen, built from the operator's study, Namport's plans and the Petroleum Act. Each item gives its status on 26 November 2026 and the source.
- Agreed terms with the government. Status: still being negotiated. In September TotalEnergies said Venus needed protecting at low oil prices and that this was under discussion with the authorities (TotalEnergies, 28 Sep 2026). The Presidency said the decision will be communicated once both sides agree (The Namibian, 4 Oct 2026).
- A final investment decision. Status: not taken. On 29 October 2026 TotalEnergies said it was "optimistic to reach the FID" (TotalEnergies Q3 transcript). The timing is covered in When will Namibia produce oil?
- A production licence. Status: none announced for any oil field. See the legal section below.
- Environmental clearance for the development. Status: final study submitted; application lodged 25 February 2025; no decision shown (SLR).
- The production ship and subsea equipment. Status: designed and priced, not ordered. In February TotalEnergies said front-end engineering was complete and the cost "firmed-up by competitive EPC bids" (TotalEnergies, 11 Feb 2026). In July its chief executive said "we have selected all contractors" (TotalEnergies, 23 Jul 2026). The study puts offshore installation about a year after the decision, over two southern-hemisphere summers.
- Development wells. Status: not started. Drilling would begin about 18 months after the decision and last up to four years (Venus study).
- Walvis Bay berths and supply base. Status: in use now, with expansion planned. Namport says Walvis Bay "remains the anchor of current exploration and drilling activity", has Namibia's first liquid mud plant, and has had its entrance channel deepened and widened (Namport annual report 2026). Its October 2025 plan uses South Port berths 7, 8 and 9 (11 m below chart datum) in the short term, with a modification to Berth 9. In the long term it plans a privately financed North Port supply base on 100 hectares of reclaimed land with at least 1,200 m of berth at 16 m depth (Namport, 6 Oct 2025).
- Lüderitz quay and supply base. Status: planned; proposals for a private supply base closed in October 2026. Namport's 2025 plan for Robert Harbour was a 500 m quay wall at 9 m depth, estimated at N$4 billion, with 300 m reserved for oil and gas. It aimed for an EPC tender "by 2026" and a first section in 2027 (Namport, 6 Oct 2025). Its 2026 annual report says preparatory work progressed, but "progress depends on securing buy-in from local Traditional Authorities". Separately, the Lüderitz Bay supply base, a multi-user base under a design-build-operate-transfer concession, closed for proposals on 26 October 2026 (Namport). More in Lüderitz and oil and gas.
- Shuttle tankers, the transfer buoy and helicopters. Status: part of the Venus project scope, so they follow a decision. The buoy would sit about 5 km off the coast north of Walvis Bay; helicopters would use existing airports, mainly Lüderitz (Venus study).
- People and towns. Status: a known gap. Deloitte's 2024 Industrial Baseline Survey, commissioned by TotalEnergies and Shell, found that "Specific O&G qualifications do not exist in-country" (Deloitte). The Venus partners say they are "committed to investing in an Upstream Oil & Gas institute". Their study notes that Lüderitz and Walvis Bay "currently struggle to keep up with the supply of land and services". Namport's 2025 plan says Lüderitz town will need to grow "to a scale that is double what it is today".
- Local content rules. Status: policy, not law. The draft National Upstream Petroleum Local Content Policy (August 2026) requires a Local Content Plan from each operator, including with the Field Development Plan that supports a production licence (draft policy). See Namibia's local content policy.
What does the law require before production?
Under the Petroleum (Exploration and Production) Act 1991, which still governs the Venus talks, a commercial find goes through three steps (Legal Assistance Centre, annotated Act):
- Declaration of a petroleum field. If a discovery is of commercial interest, the Minister declares a petroleum field by notice in the Government Gazette on the licence holder's application (section 42).
- Production licence application. It must include, among other things, an estimate of the petroleum in the reservoir, the expected start date and capacity, the sales arrangements, measures against pollution and separate decommissioning plans (section 46).
- Licence term. A production licence lasts up to 25 years, and can be renewed once for up to 10 more (section 45).
The amendment bill in Parliament would move some of the Minister's powers to the President, and decisions now taken by the Minister and the Petroleum Commissioner would pass to the Upstream Petroleum Unit in the Presidency (The Namibian, 21 Oct 2026). It is not law as of that report. Check the current text, or ask a Namibian lawyer, before relying on it.
What has already been bought?
Some preparation is already paid for. CrewDog keeps a record of 169 contract awards published by NAMCOR and Namport (137 Namport, 32 NAMCOR), read from their procurement pages; this snapshot is from 26 November 2026. We searched the award titles for oil and gas terms and for work at the two ports. The awards tied to this build-out are:
- Supply base advice: "Transactional Advisory Services in Oil & Gas Supply Base Operations" for Namport (reference CS/RFP/NAMPORT-3678/2025). The notice describes the job as help with "drafting tender documentation and conditions of contracts for appointments of independent supply base operators". Bids were invited on 5 September 2025 and closed on 3 November 2025, and the evaluation committee recommended Haskoning Nederland B.V. on 16 January 2026 (Namport evaluation summary).
- Survey: a topographic and LiDAR survey of the oil and gas terminal in the Port of Walvis Bay (Namport, reference dated 2025).
- Spill response: two awards for complete offshore oil sea booms, one for Lüderitz and one for Walvis Bay (Namport, references dated 2025).
- Lüderitz port works: two 25-ton rough-terrain mobile cranes and a paved perimeter road at the Port of Lüderitz (Namport, references dated 2025). Namport's annual report lists the new perimeter road alongside the preparatory work for the Robert Harbour quay wall.
None of the 14 notices open on 26 November 2026 is for a supply base, berth or quay. Namport ran the Lüderitz Bay supply base as its own request for proposals. Our contract awards page lists every award we hold, and our tenders page shows what is open now, checked every 12 hours.
What can a supplier do now?
Build the paperwork and relationships before the decision, because the main contracts follow it. Register on Namport's supplier portal so you can see its notices and download bid documents. Then watch three things: the Venus decision, Namport's choice for Lüderitz Bay, and the Robert Harbour EPC tender.
Sources
- SLR Environmental Consulting (Namibia) for TotalEnergies EP Namibia, Venus Field Development ESIA non-technical summary, Oct 2025: https://cdn.sanity.io/files/b0ecix6u/production/5f020d69668168da7fc72e34ab92e96c8e40747d.pdf
- SLR, ESIA for the proposed development of the offshore Venus field, public documents page, 12 Jan 2026: https://www.slrconsulting.com/afr/public-documents/ESIA-Venus-Offshore-dev/
- Namport, RFP/OIB/NAMPORT-3768/2026 Lüderitz Bay Integrated Oil and Gas Supply Base, read 26 Nov 2026: https://www.namport.com.na/procurement/926/
- Namport, Integrated Annual Report 2026 (year to 31 Mar 2026), Sep 2026: https://www.namport.com.na/files/documents/16c_Integrated%20Annual%20Report%20%202026.pdf
- Namport, Registration Portal, read 26 Nov 2026: https://www.namport.com.na/registration-portal/
- Namport, General ports update: oil and gas supply base focus, 6 Oct 2025: https://www.namport.com.na/files/procurement/87c_NAMPORT%20OIL%20AND%20GAS%20SUPPLY%20BASES%20-%206%20OCT%202025%20-%20V1.pdf
- Namport, Executive summary of bid evaluation report, Transactional Advisory Services in Oil & Gas Supply Base Operations, 16 Jan 2026: https://www.namport.com.na/files/procurement/853_Executive%20Summary_Transactional%20Advisory%20Services%20in%20Oil%20&%20Gas%20Supply%20Base%20Operations,R1.pdf
- The Namibian, Petroleum bill approved, 21 Oct 2026: https://www.namibian.com.na/petroleum-bill-approved/
- The Namibian, "Treaty of Venus", 4 Oct 2026: https://www.namibian.com.na/treaty-of-venus/
- TotalEnergies, 2025 Results and 2026 Objectives presentation, 11 Feb 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_2025-results-and-2026-objectives-presentation_2026_en.pdf
- TotalEnergies, 2Q2026 earnings call transcript, 23 Jul 2026: https://www2.totalenergies.com/sites/g/files/njizac106/files/documents/totalenergies_2q26-results-transcript_2026.pdf
- TotalEnergies, 2026 Strategy and Outlook presentation transcript, 28 Sep 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_transcript-strategy-and-outlook-presentation_2026_en.pdf
- TotalEnergies, 3Q2026 earnings call transcript, 29 Oct 2026: https://totalenergies.com/sites/g/files/nytnzq121/files/documents/totalenergies_3q26-results-transcript_2026.pdf
- Deloitte, Namibia Industrial Baseline Survey summary report, 2024: https://www.deloitte.com/content/dam/assets-zone1/na/en/docs/services/risk-advisory/2024/IBS_Namibia_Summary_Report_2024.pdf
- Office of the President, Upstream Petroleum Unit, National Upstream Petroleum Local Content Policy (draft), Aug 2026 (copy hosted by economy.com.na): https://economy.com.na/wp-content/uploads/National-Upstream-Petroleum-Local-Content-Policy-2026.pdf
- Legal Assistance Centre, Petroleum (Exploration and Production) Act 2 of 1991, annotated: https://www.lac.org.na/laws/annoSTAT/Petroleum%20(Exploration%20and%20Production)%20Act%202%20of%201991.pdf
- CrewDog, Namibia contract awards and tenders pages, data as of 26 Nov 2026: https://www.crewdog.ai/namibia/contract-awards
How this was made: researched from the sources listed above, with AI help for drafting. See how we write our articles.