The Venus oil field: size, partners and the investment decision

Venus, TotalEnergies' 2022 oil find off southern Namibia: how big it is, who owns it and why the 2026 investment decision had not come by late November.

Listen to this article

AI-narrated in a natural, human-sounding voice.

Venus is the oil field TotalEnergies discovered in February 2022 in Block 2913B (PEL 56), about 290 km off southern Namibia. TotalEnergies puts its resources at about 750 million barrels of oil equivalent. As of 26 November 2026, no final investment decision had been announced: talks with the government on the terms were still going on.

Key facts

  • TotalEnergies announced the Venus-1X discovery on 24 February 2022: light oil and associated gas, with about 84 m of net oil pay (TotalEnergies).
  • The owners since 3 September 2026 are TotalEnergies 35.25% (operator), QatarEnergy 35.25%, Galp 10%, NAMCOR 10% and Impact Oil and Gas 9.5% (TotalEnergies, 3 Sep 2026).
  • TotalEnergies' plan, published on 11 February 2026: one production ship, 150,000 barrels a day, about 750 million barrels of oil equivalent, first oil in 2030 if the investment decision came in 2026 (TotalEnergies).
  • On 23 July 2026 TotalEnergies' chief executive said the company was "ready to take the FID subject to finalising discussions with the government of Namibia", The Namibian reported on 23 August 2026.
  • In mid-October 2026 the two sides were still negotiating the development terms (World Oil, 15 Oct 2026).

How big is Venus?

TotalEnergies' own figure is about 750 million barrels of oil equivalent of resources, with planned production of 150,000 barrels a day. It describes Venus as a "fully appraised discovery" (TotalEnergies, 11 Feb 2026). Galp, a partner since September 2026, describes the plan as "a 160 kbpd FPSO", meaning a production ship able to handle 160,000 barrels a day (Galp).

An FPSO (floating production, storage and offloading vessel) is a ship moored over the field that processes the oil from the wells and stores it until tankers collect it. "Barrels of oil equivalent" adds oil and gas together in one unit.

Venus lies far offshore and in deep water. NAMCOR says the discovery is about 290 km off the coast, the well was drilled to 6,296 m (NAMCOR, 24 Feb 2022), and the block lies in water up to 3,000 m deep (NAMCOR, 2 May 2025).

Not every well in the block has worked. Marula-1X, an exploration well outside the main Venus field, was "unsuccessful" (same NAMCOR release). For how Venus compares with Namibia's other finds, see the Orange Basin guide.

Who owns Venus?

The shares have changed since the discovery:

  • At discovery, 24 February 2022: TotalEnergies 40% (operator), QatarEnergy 30%, Impact Oil and Gas 20%, NAMCOR 10% (TotalEnergies).
  • January 2025: TotalEnergies 50.5% (operator), QatarEnergy 30%, Impact 9.5%, NAMCOR 10% (NAMCOR, 22 Jan 2025).
  • From 3 September 2026: TotalEnergies 35.25% (operator), QatarEnergy 35.25%, Galp 10%, NAMCOR 10%, Impact 9.5%. Galp's 10% came from TotalEnergies in a swap that made TotalEnergies operator of Galp's Mopane discovery (TotalEnergies, 3 Sep 2026).

Where does the investment decision stand?

A final investment decision (FID) is the point at which the owners formally commit the money to build the field. The Venus target has moved several times. Here is what the companies and NAMCOR have said, in date order (items 6 to 8 come from press and event reports):

  1. 6 February 2025: Africa Oil, a shareholder in partner Impact, said an FID was "expected by the end of first half 2026" (Africa Oil).
  2. 2 May 2025: NAMCOR said the FID was "targeted in early 2026", and that the partners had started the environmental and social impact assessment, with stakeholder sessions from 7 to 30 April 2025, mainly in the Erongo and Kharas regions (NAMCOR).
  3. 9 December 2025: TotalEnergies said it was working to secure "all conditions enabling a potential final investment decision in 2026" (TotalEnergies).
  4. 30 January 2026: after meeting President Nandi-Ndaitwah, TotalEnergies and Galp described a "well-defined development concept" and a potential FID in 2026 (TotalEnergies).
  5. 11 February 2026: TotalEnergies said front-end engineering design was finalised, the capital cost had been "firmed-up by competitive EPC bids", and it was engaging with the authorities "with a target for FID mid 2026" (TotalEnergies).
  6. 23 July 2026: the chief executive told investors: "Technically, I think we have selected all contractors", and that the company was ready to take the FID subject to finishing talks with the government, The Namibian reported.
  7. August 2026: at the Namibia Oil and Gas Conference, TotalEnergies' joint venture and development director said "This is not an open-ended window" and, of a forecast that the decision could slip, "2027, that's not going to work" (The Namibian, 23 August 2026).
  8. 15 October 2026: TotalEnergies Namibia's managing director said at African Energy Week that offers were in for the FPSO, the subsea equipment and the drilling, the event's organisers reported. Her warning: "Any delay will increase the cost of CAPEX" (capital spending).
  9. 29 October 2026: TotalEnergies' third-quarter results reported completing its entry into Mopane. The release did not mention a Venus decision (TotalEnergies results, Business Wire copy).

Status as of 26 November 2026: no final investment decision on Venus, and no fiscal agreement with the government, has been announced. The Presidency has said the decision "will be officially communicated" once both parties agree (The Namibian, 4 October 2026).

What is holding the decision up?

The companies say the project is technically ready and that the remaining step is agreement with the government. The Namibian reported on 4 October 2026, citing unnamed sources, that the open points included the licence period, international arbitration, tax, a stabilisation clause (protection against later changes in the law) and the new petroleum law that Parliament had not yet passed. TotalEnergies declined to comment on what it called "unsubstantiated speculation". The same report said the talks run under the 1991 Petroleum (Exploration and Production) Act; what that Act says is explained in Namibia's Petroleum Act explained.

When the first oil might come, if a decision is taken, is covered in When will Namibia produce oil?

What would Venus mean for suppliers?

The largest packages are the FPSO, the subsea equipment, and drilling and wells, according to the African Energy Week report of 15 October 2026. TotalEnergies ran those bids itself, and its chief executive said in July that it had "selected all contractors". Local service contracts are advertised on TotalEnergies Namibia's own site. On 26 November 2026 it listed six expressions of interest, all closed: e-learning portal services (closed 15 September 2026), manpower services for upstream oil and gas, open only to Namibian majority-owned firms (30 April 2026), three platform supply vessels (9 February 2026), onshore drilling waste management (1 August 2025), cleaning (30 June 2025) and travel agency services (2 June 2025) (TotalEnergies Namibia).

What CrewDog's data shows (26 November 2026)

  • Venus work is not on the state tender pages. None of the 33 NAMCOR and Namport notices CrewDog had on record on 26 November 2026 names Venus, TotalEnergies or an FPSO. CrewDog reads both buyers' procurement pages every 12 hours.
  • Lüderitz appears more often in recent awards. Namport's chief executive said TotalEnergies' operations were supported from Lüderitz (Baird Maritime reported on 15 August 2025). Of the 169 published NAMCOR and Namport awards on CrewDog's contract-awards page, 15 award notices name the Port of Lüderitz in their title. By the year in the notice reference: 2 in 2021, 1 in 2022, 1 in 2024, 6 in 2025 and 5 in 2026. They include two rough-terrain mobile cranes, a paved perimeter road and an oil sea boom (a floating barrier used against spills). We counted titles that contain "Lüderitz"; the awards are for port work, not for Venus.

A short checklist for suppliers before a Venus decision

  1. Qualify with TotalEnergies globally. Its suppliers are qualified in a database called Sequana on five criteria: technical, health and safety, compliance, sustainability and finance. Tender invitations arrive by email for the SAP Business Network portal, and TotalEnergies says "no deposit is ever required" to take part in its tenders (TotalEnergies).
  2. Watch the Namibia expression-of-interest page for new local notices, and note any ownership condition, such as the majority-Namibian rule on the manpower notice.
  3. Follow Namport's Lüderitz notices, which CrewDog lists on its tenders page with closing dates.
  4. Treat dates as targets. The investment decision dates above are targets, and the target has already moved more than once.