How cargo reaches an offshore rig off Namibia

Step by step: how pipe, mud, cement, fuel and crews get from Walvis Bay or Lüderitz to a drillship off Namibia, with every Namibian fact sourced.

Listen to this article

AI-narrated in a natural, human-sounding voice.

As of 26 November 2026, cargo for a rig off Namibia goes through a shore base at Walvis Bay or Lüderitz. It is cleared through customs and stored, drilling mud and bulk cement are prepared at the port, and supply vessels carry it all out. Crews fly out by helicopter. TotalEnergies' planned Venus development lies about 300 kilometres from shore.

Key facts

  • TotalEnergies puts its Venus development 300 km from shore and 320 km from Lüderitz, in 3,000 metres of water (TotalEnergies, October 2025).
  • Chevron's plan for drilling in block PEL 82 uses a Walvis Bay logistics base with a warehouse, laydown area and mud plant, three to four support vessels, and helicopter crew flights from Walvis Bay two to four times a week (ERM for Chevron, 3 December 2025).
  • TotalEnergies EP Namibia asked for three large platform supply vessels, each with at least 1,000 m² of clear deck, 700 m³ of marine gasoil, 350 m³ of dry bulk and 1,200 m³ of liquid mud capacity (expression of interest closing 9 February 2026, TotalEnergies Namibia).
  • Namport says platform supply vessels need 5 to 8 metres of water (Namport, 6 October 2025).
  • Under Namibia's Customs and Excise Act, a drilling platform working on the continental shelf counts as operating in Namibia, and goods carried to and from it count as carried in Namibia (section 5 of Act 20 of 1998, NamRA's annotated copy, May 2025).

Who moves what to a rig?

A drillship far offshore cannot stock itself. Everything it uses comes from a shore base by sea, and its people come and go by air. Chevron's PEL 82 plan is the clearest public description of the set-up in Namibia. Walvis Bay "will serve as the logistics hub, storing materials like pipes, drilling fluids and fuel". Support vessels stand by at the drilling site and move "equipment and materials between the drilling unit and the onshore base". Waste goes back to shore, to licensed disposal or recycling.

Operators split between the two ports. Namport's chief executive, Andrew Kanime, had told Reuters that TotalEnergies is supported from Lüderitz, and Shell and Galp from Walvis Bay (Reuters via Baird Maritime, 15 August 2025). For the ports themselves, read Walvis Bay and oil and gas and Lüderitz and oil and gas.

How does cargo get from the quay to the drillship, step by step?

This is our own outline of the chain. The Namibian details come from the sources linked; the order of steps is how offshore supply generally works.

  1. The cargo reaches Namibia. Most heavy items arrive by ship. The vessel's agent must notify Namport at least 24 hours before arrival and lodge a provisional cargo manifest at least 18 hours before arrival (Port Regulations, Government Notice 117 of 2001).
  2. It clears customs. A licensed clearing agent lodges the customs declaration on NamRA's ASYCUDA system and pays any duty and tax. Customs then assesses the entry, may inspect the goods, and releases them (NamRA, October 2023). Rented or foreign-owned equipment that will leave again can come in under temporary import (see below).
  3. It goes to the shore base. Chevron's planned Walvis Bay base has offices, a warehouse, a laydown area and a mud plant. At Walvis Bay, oil and gas work uses South Port berths 7, 8 and 9. At Lüderitz, the oil and gas sites leased in the port covered 8,700 m² in October 2025 (Namport).
  4. Mud and cement are prepared. Drilling mud is mixed and stored in liquid mud plants. Namport says Baker Hughes, Halliburton and SLB were given space at Walvis Bay's Berth 8 for them (Namport 2025 annual report). Baker Hughes' plant holds 15,000 barrels, beside a cement bulk facility (Baker Hughes, 21 November 2024).
  5. The supply vessel is loaded. Pipe, containers and baskets go on the open deck. Dry bulk such as cement goes into tanks, liquid mud into others, and fuel into the vessel's own tanks. TotalEnergies' specification shows the scale: 1,000 m² of deck, 350 m³ of dry bulk in five tanks, 1,200 m³ of liquid mud and 700 m³ of marine gasoil.
  6. It sails. Pilotage is compulsory in Namibian ports, the Port Captain allocates berths, and a ship may leave only once Namport's dues are paid or secured (Port Regulations). Venus is 320 km from Lüderitz. Chevron's PEL 82 area lies between 72 and 300 km offshore.
  7. It unloads at the rig. Deck cargo is lifted aboard by the rig's cranes, and bulk and liquids are pumped across by hose. Chevron's plan keeps vessels on standby at the site as well.
  8. Crews change by air. Chevron plans helicopter crew flights from Walvis Bay two to four times a week during drilling, staff rotations every four weeks, and fixed-wing flights from Windhoek. As Shell prepared to start drilling in block PEL 39 in April 2026, FlyNamibia ran Windhoek (Eros)–Lüderitz flights in partnership with Shell from 2 to 22 April (The Brief, 1 April 2026).
  9. Waste and spares come back. Backloads return to the base. Chevron's plan sends remaining waste and equipment to licensed disposal or recycling facilities. Temporarily imported equipment is meant to leave Namibia again; NamRA's temporary import bond covers the duty and tax that could otherwise fall due.

How does fuel reach the rig?

By supply vessel from the shore base, in Chevron's PEL 82 plan: its Walvis Bay base will store "materials like pipes, drilling fluids and fuel", and its vessels move materials between the base and the rig. Supply vessels carry large volumes of marine gasoil: TotalEnergies wanted at least 700 m³ of capacity on each. Namport lists bunkering among its services at both Walvis Bay and Lüderitz (Namport 2026 annual report).

Behind that sits Namibia's import system. NAMCOR's National Oil Storage Facility at Walvis Bay holds 75 million litres of diesel, petrol, jet fuel and heavy fuel oil in seven tanks. Its tanker jetty has two berths with a maximum draught of 16.5 metres (NAMCOR). In 2025 Namport also awarded a feasibility and safety study for simultaneous operations at two existing fuel import jetties at Walvis Bay's North Port (CrewDog's contract awards record).

One customs detail matters here. For fuel levy purposes, the Act treats a vessel stationed at an offshore exploration or production platform outside Namibia's territorial waters, and used only for that work, as a "foreign-going ship". Check the current text, or ask a Namibian lawyer, before relying on it.

How are customs handled for rig equipment?

Through a licensed clearing agent, under the Customs and Excise Act 20 of 1998. Points that come up in offshore work:

  • Offshore counts as Namibia. Section 5 deems a floating or submersible drilling or production platform on the continental shelf to be operating in Namibia, and goods and people carried to and from it to be carried in Namibia.
  • Clearing for others needs a licence. Section 73 says only a licensed clearing agent may make customs entries for reward on behalf of an importer or exporter. A firm clearing only its own goods registers for direct access to ASYCUDA instead, according to NamRA's proposed licensing rules.
  • Temporary import. NamRA's October 2023 guidance lists rebate item 490.00 for goods brought in temporarily, for example for repair or a specific purpose, or to be exported again in the same state. It gives a stay of six months, with a further six months possible on request, under a temporary import permit (NamRA also names the carnet de passage, which covers vehicles) and, where required, a surety bond that covers the duty and tax.
  • ATA carnets. NamRA accepts ATA carnets for professional equipment owned abroad, and goods under a carnet need no bond or provisional payment (NamRA).
  • Bonded warehouses. NamRA licenses customs warehouses for storing dutiable goods under section 19 (NamRA).

Check the current text, or ask a Namibian lawyer, before relying on it. What the agents themselves do is covered in shipping and clearing agents in Walvis Bay.

What should a supplier check before shipping to a Namibian shore base?

A short checklist of our own:

  • Which base and which operator? Ask the operator or its main contractor which port and base your cargo goes to.
  • Who is the importer? Agree who appears as importer on the customs entry and who pays any duty and tax.
  • Permanent or temporary import? Decide before the goods arrive. Temporary import needs a permit or carnet, and may need a bond.
  • Which clearing agent? Use one licensed by NamRA, and confirm it works at the port your cargo lands in.
  • What does the operator require for offshore cargo? Ask for its rules on packing, labelling, lifting gear and dangerous goods before you ship. Namport's arrival notice also asks for dangerous goods details.
  • How will it come back? Plan the return of rental tools and containers, and the paperwork that closes a temporary import.

Sources

  • TotalEnergies, How will the Venus oil project work?, October 2025: totalenergies.com
  • ERM for Chevron Namibia Exploration Limited II, Final ESIA and ESMP for proposed offshore drilling in PEL 82: non-technical summary, 3 December 2025: erm.com
  • TotalEnergies EP Namibia, Expression of interest for the provision of platform supply vessels, January 2026 (closed 9 February 2026): totalenergies.na
  • Namport, General ports update: oil and gas supply base focus, 6 October 2025: namport.com.na
  • Namport, Integrated Annual Report 2025, December 2025: namport.com.na
  • Namport, Integrated Annual Report 2026, September 2026: namport.com.na
  • Ministry of Works, Transport and Communication, Port Regulations, Government Notice 117 of 2001 (Namport copy): namport.com.na
  • Baker Hughes, news release on its Walvis Bay liquid mud plant and cement bulk facility, 21 November 2024: bakerhughes.com
  • NAMCOR, National Oil Storage Facility, read 26 November 2026: namcor.com.na
  • NamRA, Customs and Excise Act 20 of 1998 (annotated copy), May 2025: namra.org.na
  • NamRA, Online corner: registration and licensing of clearing agents, warehouses, transit and temporary import bonds, October 2023: namra.org.na
  • NamRA, Proposed rules for the licensing of clearing agents, February 2022: namra.org.na
  • NamRA, ATA carnets, read 26 November 2026: namra.org.na
  • NamRA, Storage and manufacturing warehouses, read 26 November 2026: namra.org.na
  • Reuters via Baird Maritime, Namibia's ports authority scraps key energy project at Luderitz, 15 August 2025: bairdmaritime.com
  • The Brief, FlyNamibia and Shell launch Eros–Lüderitz partnership flights, 1 April 2026: thebrief.com.na
  • CrewDog, Namibia contract awards, read 26 November 2026: contract awards

How this was made: researched from the sources listed above, with AI help for drafting. See how we write our articles.