As of 26 November 2026, Walvis Bay is the main shore base for offshore oil and gas work in Namibia. Namport, the ports authority, calls it "the anchor of current exploration and drilling activity". Oil and gas work uses three shared South Port berths. A Berth 9 upgrade and a North Port supply base are planned; neither has been awarded.
Key facts
- Walvis Bay has 16 commercial berths and a 16-metre main channel, and the North Port oil jetty also has 16 metres of water (Namport Integrated Annual Report 2026, year to 31 March 2026).
- Oil and gas work uses common-user berths 7, 8 and 9 in the South Port: 11 metres below chart datum, 10.5 metres maximum draught (Namport supply base presentation, 6 October 2025).
- Seven applications were opened on 29 January 2026 for the Berth 9 Modification Project's construction contract (Namport bid opening record). No award had been published by 26 November 2026.
- Namport's long-term plan is a privately built supply base at the North Port, on 100 hectares of reclaimed land with at least 1,200 metres of quay (Namport, 6 October 2025). No tender for it was on Namport's bid opening register on 26 November 2026.
- Baker Hughes opened a liquid mud plant, a cement bulk facility and a multi-modal facility at the port on 21 November 2024 (Baker Hughes).
- 25 companies in CrewDog's Namibia directory name Walvis Bay among their towns (CrewDog count, 26 November 2026).
What is the Port of Walvis Bay?
It is Namibia's main commercial port. The Namibian Ports Authority (Namport), a state-owned company set up under the Namibian Ports Authority Act 2 of 1994, owns and runs it. Namport also runs the Port of Lüderitz, 254 nautical miles to the south.
Namport's 2026 annual report gives these figures for Walvis Bay:
- 16 commercial berths
- a main channel 16 metres deep, and 16 metres at the North Port oil jetty
- container capacity of 750,000 TEU (twenty-foot equivalent units) a year and break-bulk capacity of 10 million tonnes a year
- open 24 hours a day, seven days a week
- bunkering, ship chandling, towage, pilotage and "oil and gas services" among the services it lists
The port has three parts: the South Port, the Fishing Harbour and the North Port, the newest section (Namport, October 2025). Namport's two existing fuel import jetties are at the North Port, as a 2025 Namport award for a safety study there makes clear. The 2026 annual report says entrance channel dredging "further strengthened Walvis Bay's deepwater capability" in the year to March 2026.
Which berths do oil and gas ships use today?
Shared ones. Namport's October 2025 plan names South Port berths 7, 8 and 9 as the short-term oil and gas supply base. They are common-user general cargo berths with heavy-lift capacity. Namport said this set-up would suffice for "3-5 years at most": the rest of exploration, plus the first one or two years of developing the Venus field. Land inside the port is being topped up with land in town.
Space for drilling mud plants is at Berth 8. Namport's 2025 annual report says Baker Hughes, Halliburton and SLB "were allocated space at Berth 8 to establish Liquid Mud Plants" for the exploration wells. Baker Hughes says its plant holds 15,000 barrels of drilling and completion fluids.
Namport expects demand to jump. Its October 2025 plan says the development phase "will commence with TOTALENERGIES in 2027" and needs about ten times the port capacity of exploration. That timing depends on an investment decision.
Status as of 26 November 2026: we found no announcement of a final investment decision on Venus. The Namibian reported on 4 October 2026 that the government and TotalEnergies were still in talks.
What is the Berth 9 Modification Project?
A rebuild of Berth 9 to unlock more capacity at the shared berths. On 21 November 2025 Namport invited firms to apply for initial selection (a pre-qualification step) for an engineering, procurement and construction (EPC) contract, reference ISD/EPC/NAMPORT-3694/2025. Namport's notice says the work may include:
- a concrete or steel quay wall, bridge and deck
- changes to the existing jetty
- dredging and land reclamation
- ground improvement and road works
Applications closed on 29 January 2026, and the bid opening record lists seven. Namport also ran a separate tender for the project's environmental impact assessment, opened on 3 October 2025 according to its bid opening register. Its 2026 annual report says the project "progressed through prequalification and contractor shortlisting".
Status as of 26 November 2026: no award or cancellation for the Berth 9 contract appears on Namport's award or cancellation lists, and we found no published shortlist.
What is planned at the North Port?
A dedicated supply base, in the long run. Namport's October 2025 plan describes a greenfield oil and gas base at the North Port, to be developed by a private company as a design, build, own, operate and transfer (DBOOT) concession:
- 100 hectares of back-up land, reclaimed with material dredged from the new basin
- 1,200 metres or more of quay, 16 metres below chart datum
- room for all the supply base work now done in the South Port
Namport's 2026 annual report adds that the South Port "remains constrained by land availability" while the North Port "has sufficient land". It also says Namport "continued discussions with SONILS on developing an onshore oil and gas supply base at Walvis Bay North Port".
Namport has already awarded studies. CrewDog's record of Namport's published awards includes four from 2025 (values as stated in each notice, which we have not adjusted):
- transactional advisory services for oil and gas supply base operations, awarded to Haskoning Nederland B.V.
- engineering consulting for road and land infrastructure at the North Port, about N$2.1 million
- a feasibility and safety study for simultaneous operations at the two existing fuel import jetties at the North Port, N$5,994,207
- a topographic and LiDAR survey of "the oil and gas terminal" in the port, N$101,000
Status as of 26 November 2026: Namport's bid opening register shows no tender yet for a North Port supply base concession.
Who is already working from Walvis Bay?
Operators, service companies and local firms:
- Shell and Galp. Namport's chief executive, Andrew Kanime, had told Reuters that Shell and Galp are backed by Walvis Bay, while TotalEnergies is supported from Lüderitz (Reuters, published by Baird Maritime on 15 August 2025).
- Chevron (planned). Chevron's environmental assessment for drilling in block PEL 82, dated 3 December 2025, names Walvis Bay as its logistics base, with offices, a warehouse, a laydown area and a mud plant. Crews would fly to the rig by helicopter from Walvis Bay. It gives 2026/2027 as the expected timing (ERM for Chevron).
- Service companies. Baker Hughes, with its mud plant, cement bulk facility and multi-modal facility. Halliburton and SLB, which Namport says were given space at Berth 8 for mud plants.
- NAMCOR. The national oil company's National Oil Storage Facility at Walvis Bay holds 75 million litres in seven tanks, with a two-berth tanker jetty. Commissioning finished in February 2021.
- Local firms. In CrewDog's Namibia company directory, 25 companies name Walvis Bay among their towns. By service: logistics and transport 11, shipping agency and clearing 10, marine services 8, warehousing and storage 8, industrial supplies 4, and smaller numbers in other services. A company can sit in more than one service. We counted on 26 November 2026, in a directory last built from named public sources on 15 November 2026. 213 of its 248 companies give no town at all, so treat 25 as a minimum.
How can a Walvis Bay firm follow this work?
Four places to watch:
- Namport's procurement pages. Bids, awards, cancellations and the bid opening register are public. Bid opening records name the firms that applied, for example for Berth 9, which tells local subcontractors who may need partners. To bid yourself you must register as a Namport supplier: see Namport procurement: how to register and bid.
- CrewDog's tender tracker. Namibia tenders reads NAMCOR's and Namport's procurement pages every 12 hours. On 26 November 2026 it showed 12 open Namport notices.
- The operators. Oil companies buy through their own supplier systems, not through Namport, so a port contract and an operator contract are separate routes.
- Lüderitz. Some of the work will go south. See Lüderitz and oil and gas, and for the journey from quay to rig, how cargo reaches an offshore rig off Namibia.
Sources
- Namport, Integrated Annual Report 2026 (year to 31 March 2026), September 2026: namport.com.na
- Namport, Integrated Annual Report 2025, December 2025: namport.com.na
- Namport, General ports update: oil and gas supply base focus, 6 October 2025: namport.com.na
- Namport, Initial selection notice for the Berth 9 Modification Project EPC contract, ISD/EPC/NAMPORT-3694/2025, November 2025: namport.com.na
- Namport, Bid opening record, ISD/EPC/NAMPORT-3694/2025, 29 January 2026: namport.com.na
- Namport, Bid Opening Register, read 26 November 2026: namport.com.na
- Namport, Notice of Bids Awarded, read 26 November 2026: namport.com.na
- Namport, Notice of Bids Cancelled, read 26 November 2026: namport.com.na
- Baker Hughes, news release on its Walvis Bay liquid mud plant, cement bulk facility and multi-modal facility, 21 November 2024: bakerhughes.com
- ERM for Chevron Namibia Exploration Limited II, Final ESIA and ESMP for proposed offshore drilling in PEL 82: non-technical summary, 3 December 2025: erm.com
- NAMCOR, National Oil Storage Facility, read 26 November 2026: namcor.com.na
- Reuters via Baird Maritime, Namibia's ports authority scraps key energy project at Luderitz, 15 August 2025: bairdmaritime.com
- The Namibian, Treaty of Venus, 4 October 2026: namibian.com.na
- CrewDog, Namibia contract awards, companies and tenders, read 26 November 2026: contract awards, companies, tenders
How this was made: researched from the sources listed above, with AI help for drafting. See how we write our articles.